A professional supplier for sandwich panel and prefab house
Foshan YAJ Building Co.,Ltd
E-mail: yaj@yajbuilding.com
86-13760920214
1.Sandwich Panel Carry
1)For panels’length below 4.0 meter, 2~4 pieces per time by two persons, one stands in front, on stands behind.
2)For the panels’length more than 4.0 meters, 1 piece per time by 4~8 persons, the persons should be distributed on average based on the panels’length, there should be persons each 2.5 meters distance on left and right side.
3)When carrying the panels, it should hold the whole panel, not just the top steel sheet.
The right way (√) | |
The wrong way(х) | |
(the wrong carrying way of sandwich panel will cause the damage as bellows) | |
(carry the panel a little high when unloading, especially the location close to the roof wave, to prevent scratching the panel surface) |
|
2.The windows'carry
The wrong way (√) | The right way (√) |